Construction Obstruction Report: May 2016

UNT MAIN CAMPUS

Flag #1               NORTH TEXAS BOULEVARD / I-35 INTERSECTION-NORTH                   

Location:  Intersection of North Texas Boulevard and I-35 and various surrounding streets

Project Lead: AGL/City of Denton/Helen Bailey

Duration: September 2015 to spring 2017

Description:  Realignment of the frontage roads, construction on the new North Texas Boulevard bridge will cause closures of various streets and may cause obstruction of walkways.

 

Flag #2                 SCIENCE RESEARCH BUILDING ENVELOPE AND INTERIOR

Location: East and south sides of building, 1ST floor, mechanical

Project Lead: Julie Sands and Janna Morgan

Duration: December 2015 to December 2016

Description: Interior renovation of 1st floor, MEP, accessibility. Sidewalks and parking spots will be blocked by job site perimeter fencing for the duration of the project.

 

Flag #3                 UNION CONSTRUCTION AND LANDSCAPING         

Location:  University Union, By Highland Street

Project Lead: Jeannine Vail

Duration: April 2013 to May 2016

Description:   University Union landscape work continues. Sidewalk on Highland Street obstructed while demolition is in progress.

 

Flag 4                   RAWLINS HALL                      

Location:  Corner of Maple Street, Avenue D, and Eagle Blvd (west of Honors Hall and Clark Hall)

Project Lead: Janna Morgan

Duration: May 2014 to May 2016

Description:  Site work to the west courtyard.  Street and sidewalk closures to be expected.

 

Flag #5                 MAPLE HALL LOADING DOCK DRIVEWAY

 

Location: Maple Hall loading dock off South Avenue C

Project Lead: Jeff Hilliard

Duration: June 2016

Description: Remove and replace Maple Dining Hall concrete drive and side walk. May cause obstruction of walkways.

 

Flag #6                 BOOKSTORE TENT DEMOLITION

Location: South of McConnell Hall on Chestnut Street

Project Lead: Jeannine Vail

Duration: December 2015 to May 2016

Description: Demolition may cause closure of sidewalks on Chestnut Street.

 

Flag #7                 LOT #49

Location: East of the University Union, Lot #49

Project Lead: Jeannine Vail

Duration: April 2013 to May 2016

Description: Construction crew and equipment using lot for landscape work may cause obstruction of walkways.

 

Flag #8                 LANGUAGE BUILDING

Location: The plaza: north, east, and south sides of the building

Project Lead: Sharon Kirkpatrick

Duration: April 2016 to August 2016

Description: Renovation of building plaza.  Includes removal and replacement of concrete, sub-soil drains, access ramp, and planter.  May cause obstruction of walkways.

 

Flag #9                 CLARK HALL

Location: Northeast side of building

Project Lead: Jeff Hilliard

Duration: December 2015 to May 2016

Description: Contractor will tie-in fire pump to city water line on Maple Street blocking portions of the sidewalk.

 

Flag #10               COLLEGE INN BREEZEWAY

Location: Breezeway adjacent to College Inn courtyard, near main office.

Project Lead: Monica Thomas

Duration: May 2016 to July 2016

Description: Addition of exterior egress stairway to be constructed. Breezeway to be blocked at different periods of assembly

 

Flag #11               Lot #5

Location: Parking lot on east side of Chestnut Hall

Project Lead: Charlie Scaife

Duration: May 2016 to August 2016

Description: Lot Five will be closed through the duration of McConnell Hall Construction in 2016. Large construction equipment will impede access to parking lot.

 

Flag #12               BRUCE HALL RENOVATION

Location: North, West, East, and dock areas of Bruce Hall

Project Lead: Ed Carrigan

Duration: May 2016 to August 2016

Description: Periodic closure of streets and sidewalks for delivery of equipment and materials.

 

Posted on: Mon 16 May 2016

Owning Excellence

Faculty and staff members have roles in transforming UNT into a nationally prominent university. Share your ideas on how you can help UNT to own excellence, keep students on track and improve graduation education.

Mean Green Pride

Deadlines

No current Deadlines

UNT Calendar

September 25, 2017 - 11:00am
September 25, 2017 - 1:00pm
September 25, 2017 - 1:00pm

Archives